Retrofitting and Upgrade of the Muzha Incineration Plant

Taiwan

Project Factsheet

After more than 20 years of continuous operation, the Muzha Refuse Incineration Plant required a comprehensive upgrade to meet rising waste heating values and increasingly stringent emission standards. The retrofit aimed to enhance waste treatment capacity, modernize the entire flue gas cleaning system, and restore the electrical infrastructure to accommodate higher power output. Special features of the project included executing all upgrade measures during ongoing plant operation, replacing the electrostatic precipitator with membrane bag filters, renewing key systems such as the ID fan and SNCR, and completing structural improvements including a full repainting of the 150 meter stack. Additional renovations to various buildings rounded off the modernization effort. To ensure the project’s successful execution from concept to commissioning, Fichtner provided engineering and project management support throughout all phases.

Incineration lines
Total thermal treatment capacity after retrofit
Net power generation
Key Facts

Modernization of the Muzha Refuse Incineration Facility

  • Bid engineering
  • Support during proposal preparation
  • Project management assistance
  • Basic and detailed design
  • Specification and clarification during procurement
  • Technical support during manufacturing
  • Technical support during construction
  • Preparation and supervision of trial run & performance test
  • 4 incineration lines, 300 t/d each 
  • Net power generation: 13.5 MWe
  • Dust emissions: 80 mg/Nm³
  • HCl emissions: 40 ppm
  • SOx emissions: 80 ppm
  • NOx emissions: 180 ppm
  • Dioxin emissions: 0.1 ng‑TEQ/Nm³

Client

Chung-Hsin Electric and Machinery Manufacturing Corp.

Taipei
Taiwan